We have finished another complex factory installation

Anko Rejinders
28/05/2024 10:00:00

Not so long ago we have finished another complex factory installation job.
We were contracted to design, produce and assemble conveying tracks that needed to be placed in 3 different halls to separate product assembly from storage and transport.
We ended up building tracks measuring a total distance of some 350 meters.
In the tracks we placed over 750 meters of conveyorbelts, some 600 conveyorrollers and 50 drummotors.
We are proud to say that everyting is moving smoothly.